Scheduling cases
You can schedule a test case to run automatically at a time you specify. You can also specify a repeat interval (once, hourly, daily, weekly, monthly).
To configure a schedule:
- Go to Schedules under either Cases > Performance Testing or Cases > Security Testing.
- Click + Create New to display the configuration page.
- Enter a name for the schedule.
- Select Enable to enable this schedule.
- Enter a delay between test cases.
- In Settings, select the start date and time, and the repeat option.
- In Case Setting, select one or more cases, then click to confirm the selection.
- Click Save to save the schedule configuration.
Tip: To set up a schedule from the case list, click the icon to display the schedule configuration page.