You can change a task from a Repetitive task to a Fixed Day task by changing the task’s date, time, and repetition rate. You can also change the group associated with the task and the name of the task . For field definitions see Add a task within the scheduler.

  1. Select System > Scheduler.
  2. Use the filters to display a list of tasks.
  3. Click the task to select it.
  4. Click Modify.
  5. Modify the data as needed.
  6. Click OK.

Modify a task

You can change a task from a Repetitive task to a Fixed Day task by changing the task’s date, time, and repetition rate. You can also change the group associated with the task and the name of the task . For field definitions see Add a task within the scheduler.

  1. Select System > Scheduler.
  2. Use the filters to display a list of tasks.
  3. Click the task to select it.
  4. Click Modify.
  5. Modify the data as needed.
  6. Click OK.